CAP · Question #27
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
The correct answer is D. Transference. Transferring risk means shifting the financial or operational burden of a risk to a third party, such as a vendor or contractor.
Question
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
Options
- AAvoidance
- BMitigation
- CExploit
- DTransference
How the community answered
(62 responses)- A3% (2)
- B6% (4)
- C13% (8)
- D77% (48)
Why each option
Transferring risk means shifting the financial or operational burden of a risk to a third party, such as a vendor or contractor.
Avoidance means changing the project plan to eliminate the risk entirely, not delegating it to another party.
Mitigation reduces the probability or impact of a risk but keeps the risk within the project rather than transferring it.
Exploit is a positive risk response strategy used to maximize opportunities, not to handle threats.
Risk transference involves assigning the responsibility and consequences of a risk to an outside party, typically through contracts, warranties, or outsourcing agreements. By hiring a company to handle all hardware work, the project manager moves the hardware-related risk exposure to that vendor, making transference the correct response strategy.
Concept tested: Risk transference response strategy in PMBOK
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.