nerdexam
(ISC)2(ISC)2

CAP · Question #22

CAP Question #22: Real Exam Question with Answer & Explanation

The correct answer is B: Approximately 11 months. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager for your organization. You have identified a risk event you're your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor's solution?

Options

  • AApproximately 13 months
  • BApproximately 11 months
  • CApproximately 15 months
  • DApproximately 8 months

Topics

#Risk management#Cost-benefit analysis#Risk response options#Financial comparison

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions