nerdexam
(ISC)2(ISC)2

CAP · Question #126

CAP Question #126: Real Exam Question with Answer & Explanation

The correct answer is D: Sharing. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use the procurement processes?

Options

  • AAcceptance
  • BMitigation
  • CExploiting
  • DSharing

Topics

#Risk Management#Risk Response Strategies#Risk Sharing#Procurement

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions