(ISC)2(ISC)2
CAP · Question #120
CAP Question #120: Real Exam Question with Answer & Explanation
The correct answer is D: The level of detail should correspond with the priority ranking. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?
Options
- AThe level of detail is set by historical information.
- BThe level of detail must define exactly the risk response for each identified risk.
- CThe level of detail is set of project risk governance.
- DThe level of detail should correspond with the priority ranking
Topics
#Risk Management#Risk Response#Risk Register#Prioritization
Community Discussion
No community discussion yet for this question.