nerdexam
(ISC)2(ISC)2

CAP · Question #119

CAP Question #119: Real Exam Question with Answer & Explanation

The correct answer is B: Risk distributions within the project schedule. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?

Options

  • AProbability of achieving cost and time objectives
  • BRisk distributions within the project schedule
  • CProbabilistic analysis of the project
  • DTrends in quantitative risk analysis

Topics

#Quantitative Risk Analysis#Risk Register#Project Risk Management#Risk Communication

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions