(ISC)2(ISC)2
CAP · Question #119
CAP Question #119: Real Exam Question with Answer & Explanation
The correct answer is B: Risk distributions within the project schedule. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?
Options
- AProbability of achieving cost and time objectives
- BRisk distributions within the project schedule
- CProbabilistic analysis of the project
- DTrends in quantitative risk analysis
Topics
#Quantitative Risk Analysis#Risk Register#Project Risk Management#Risk Communication
Community Discussion
No community discussion yet for this question.