Creating a baseline of current performance generally happens in which phase of the Plan-Do- Check-Act cycle?

The correct answer is A. Plan. See the full explanation below for the reasoning.

Question

Creating a baseline of current performance generally happens in which phase of the Plan-Do- Check-Act cycle?

Options

  • APlan
  • BDo
  • CCheck
  • DAct

How the community answered

(41 responses)
  • A
    73% (30)
  • B
    7% (3)
  • C
    15% (6)
  • D
    5% (2)