Software
CABA · Question #240
Who is responsible for creating and maintaining the overall test plan to reflect changes to the overall project plan?
The correct answer is B. Test Manager. See the full explanation below for the reasoning.
Question
Who is responsible for creating and maintaining the overall test plan to reflect changes to the overall project plan?
Options
- AProject Manager
- BTest Manager
- CBusiness Analyst
- DUser
How the community answered
(28 responses)- A4% (1)
- B79% (22)
- C4% (1)
- D14% (4)
Community Discussion