During what type of review would an examination of a specific project be done to determine what worked, what did not work and what should be changed for the future.

The correct answer is B. Post Implementation Review. See the full explanation below for the reasoning.

Question

During what type of review would an examination of a specific project be done to determine what worked, what did not work and what should be changed for the future.

Options

  • ACheckpoint Review
  • BPost Implementation Review
  • CPhase End Review
  • DNone of the above

How the community answered

(55 responses)
  • A
    16% (9)
  • B
    73% (40)
  • C
    7% (4)
  • D
    4% (2)