Software
CABA · Question #212
During what type of review would an examination of a specific project be done to determine what worked, what did not work and what should be changed for the future.
The correct answer is B. Post Implementation Review. See the full explanation below for the reasoning.
Question
During what type of review would an examination of a specific project be done to determine what worked, what did not work and what should be changed for the future.
Options
- ACheckpoint Review
- BPost Implementation Review
- CPhase End Review
- DNone of the above
How the community answered
(55 responses)- A16% (9)
- B73% (40)
- C7% (4)
- D4% (2)
Community Discussion
No community discussion yet for this question.