In the EVM concept, a SPI greater than 1 indicates:
The correct answer is C. 100% or less of the planned time has been used to complete the scheduled work. See the full explanation below for the reasoning.
Question
In the EVM concept, a SPI greater than 1 indicates:
Options
- ALess of the budget was consumed for the work
- BExcess of the budget have been spent for the actual work completed
- C100% or less of the planned time has been used to complete the scheduled work
- DMore than planned time has been used to complete the scheduled work
How the community answered
(46 responses)- A9% (4)
- B11% (5)
- C76% (35)
- D4% (2)