In the EVM concept, a SPI greater than 1 indicates:

The correct answer is C. 100% or less of the planned time has been used to complete the scheduled work. See the full explanation below for the reasoning.

Question

In the EVM concept, a SPI greater than 1 indicates:

Options

  • ALess of the budget was consumed for the work
  • BExcess of the budget have been spent for the actual work completed
  • C100% or less of the planned time has been used to complete the scheduled work
  • DMore than planned time has been used to complete the scheduled work

How the community answered

(46 responses)
  • A
    9% (4)
  • B
    11% (5)
  • C
    76% (35)
  • D
    4% (2)