CABA · Question #203

The final product of the Pre-Requirements Analysis phase is the:

The correct answer is A. Feasibility Study. See the full explanation below for the reasoning.

Question

The final product of the Pre-Requirements Analysis phase is the:

Options

  • AFeasibility Study
  • BPreliminary Benefit Estimate
  • CPreliminary Scope Statement
  • DRequirements Definition

How the community answered

(60 responses)
  • A
    72% (43)
  • B
    7% (4)
  • C
    18% (11)
  • D
    3% (2)