The final product of the Pre-Requirements Analysis phase is the:
The correct answer is A. Feasibility Study. See the full explanation below for the reasoning.
Question
The final product of the Pre-Requirements Analysis phase is the:
Options
- AFeasibility Study
- BPreliminary Benefit Estimate
- CPreliminary Scope Statement
- DRequirements Definition
How the community answered
(60 responses)- A72% (43)
- B7% (4)
- C18% (11)
- D3% (2)