As the Business Analysis activity advances due to budgetary constraints, the Business Partner has asked the Project Manager to focus the effort of the subsequent work only on the most critical…

The correct answer is C. Prioritize Requirements. See the full explanation below for the reasoning.

Question

As the Business Analysis activity advances due to budgetary constraints, the Business Partner has asked the Project Manager to focus the effort of the subsequent work only on the most critical requirements. What must the Business Analyst do?

Options

  • AElicit Requirements
  • BDrop Requirements
  • CPrioritize Requirements
  • DValidate Requirements

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    75% (18)
  • D
    13% (3)