The Project Manager of Project Alpha is creating a project plan. Which one of the following would be an example of a sub-activity in this scenario?

The correct answer is A. Create a Test Plan. See the full explanation below for the reasoning.

Question

The Project Manager of Project Alpha is creating a project plan. Which one of the following would be an example of a sub-activity in this scenario?

Options

  • ACreate a Test Plan
  • BDevelop Code
  • CPerform Testing
  • DManage Changes

How the community answered

(23 responses)
  • A
    83% (19)
  • B
    4% (1)
  • C
    4% (1)
  • D
    9% (2)