The Project Manager of Project Alpha is creating a project plan. Which one of the following would be an example of a sub-activity in this scenario?
The correct answer is A. Create a Test Plan. See the full explanation below for the reasoning.
Question
The Project Manager of Project Alpha is creating a project plan. Which one of the following would be an example of a sub-activity in this scenario?
Options
- ACreate a Test Plan
- BDevelop Code
- CPerform Testing
- DManage Changes
How the community answered
(23 responses)- A83% (19)
- B4% (1)
- C4% (1)
- D9% (2)