Which two options can you define in Customizing for Logistics Invoice Verification to manage unplanned delivery costs for invoice receipts? (Choose two.)

The correct answer is B. The unplanned delivery costs are to be posted to a separate G/L account for unplanned delivery costs. C. The unplanned delivery costs are to be split across the invoice items. See the full explanation below for the reasoning.

Question

Which two options can you define in Customizing for Logistics Invoice Verification to manage unplanned delivery costs for invoice receipts? (Choose two.)

Options

  • AThe unplanned delivery costs are to be posted to a price difference account.
  • BThe unplanned delivery costs are to be posted to a separate G/L account for unplanned delivery costs.
  • CThe unplanned delivery costs are to be split across the invoice items.
  • DThe unplanned delivery costs are to be posted to a specific cost center.

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    73% (24)
  • D
    18% (6)