What information can you specify in a quota arrangement? (Choose two.)
The correct answer is A. Plant from which material is procured for stock transfer requirements C. Vendor for external procurement requirements. See the full explanation below for the reasoning.
Question
What information can you specify in a quota arrangement? (Choose two.)
Options
- APlant from which material is procured for stock transfer requirements
- BOutline agreement number for external procurement requirements
- CVendor for external procurement requirements
- DInfo record number for external procurement requirements
How the community answered
(60 responses)- A73% (44)
- B8% (5)
- D18% (11)