SAP
C_TSCM52_65 · Question #54
At what level can you set quantity and value updating on a material type?
The correct answer is C. Valuation area. See the full explanation below for the reasoning.
Question
At what level can you set quantity and value updating on a material type?
Options
- APlant
- BCompany code
- CValuation area
- DProcurement type
How the community answered
(41 responses)- A15% (6)
- B2% (1)
- C76% (31)
- D7% (3)
Community Discussion