Which procurement elements can be generated in the material requirements planning run for a material that is procured only externally? (Choose three.)

The correct answer is A. Planned orders B. Purchase requisitions C. Schedule lines. See the full explanation below for the reasoning.

Question

Which procurement elements can be generated in the material requirements planning run for a material that is procured only externally? (Choose three.)

Options

  • APlanned orders
  • BPurchase requisitions
  • CSchedule lines
  • DPurchase orders
  • EProduction orders

How the community answered

(26 responses)
  • A
    69% (18)
  • D
    12% (3)
  • E
    19% (5)