C_TSCM52_65 · Question #5
You transfer material between two plants. During the transport process, some parts are damaged so badly that they have to be scrapped. How you can you post this as scrapping? (Choose two.)
The correct answer is A. You reverse the stock removal in the issuing plant and post the scrapping there. B. You put away the entire quantity in the receiving plant and post the scrapping there. See the full explanation below for the reasoning.
Question
You transfer material between two plants. During the transport process, some parts are damaged so badly that they have to be scrapped. How you can you post this as scrapping? (Choose two.)
Options
- AYou reverse the stock removal in the issuing plant and post the scrapping there.
- BYou put away the entire quantity in the receiving plant and post the scrapping there.
- CYou adjust the stock in transit and put away the remaining quantity in the receiving plant.
- DYou put away the entire quantity in the receiving plant, where you immediately carry out a physical
How the community answered
(49 responses)- A84% (41)
- C6% (3)
- D10% (5)