The correct answer is B. The new price is immediately proposed for all new purchase orders created for the relevant material. See the full explanation below for the reasoning.
Question
You change the price for the current validity period in an info record. There are still two purchase SAP C_TSCM52_65 Exam orders for this material that are open for delivery from the relevant vendor. What happens when the price is changed in the info record?
Options
- AThe moving average price of the material is recalculated.
- BThe new price is immediately proposed for all new purchase orders created for the relevant material
- CThe PO price in the purchase orders that are still open is automatically changed to the new price.
- DInvoice verification automatically receives a message about the price change made.