nerdexam
SAP

C_TSCM52_65 · Question #3

Which of the following is a prerequisite for transfer postings between two materials ("material to material")?

The correct answer is D. The materials being transferred must have the same base unit of measure. See the full explanation below for the reasoning.

Question

Which of the following is a prerequisite for transfer postings between two materials ("material to material")?

Options

  • AThe materials being transferred must have the same valuation class.
  • BThe materials being transferred must have the same material type.
  • CThe materials being transferred must have the same material group.
  • DThe materials being transferred must have the same base unit of measure.

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    12% (4)
  • C
    6% (2)
  • D
    79% (26)

Community Discussion

No community discussion yet for this question.

Full C_TSCM52_65 Practice