nerdexam
SAP

C_TSCM44_65 · Question #73

Your customer is using the ECC planning transaction for repetitive manufacturing as shown in the screenshot. Which planning transaction in SCM do you have to configure to offer the same "look and…

The correct answer is D. Product planning table. See the full explanation below for the reasoning.

Question

Your customer is using the ECC planning transaction for repetitive manufacturing as shown in the screenshot. Which planning transaction in SCM do you have to configure to offer the same "look and feel"?

Exhibit

C_TSCM44_65 question #73 exhibit

Options

  • AProduction campaign transaction
  • BResource planning table
  • CProduct view: Periods tab layout definition
  • DProduct planning table

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    14% (5)
  • D
    77% (27)

Community Discussion

No community discussion yet for this question.

Full C_TSCM44_65 Practice