SAP
C_TSCM44_65 · Question #73
Your customer is using the ECC planning transaction for repetitive manufacturing as shown in the screenshot. Which planning transaction in SCM do you have to configure to offer the same "look and…
The correct answer is D. Product planning table. See the full explanation below for the reasoning.
Question
Your customer is using the ECC planning transaction for repetitive manufacturing as shown in the screenshot. Which planning transaction in SCM do you have to configure to offer the same "look and feel"?
Exhibit
Options
- AProduction campaign transaction
- BResource planning table
- CProduct view: Periods tab layout definition
- DProduct planning table
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C14% (5)
- D77% (27)
Community Discussion
No community discussion yet for this question.