nerdexam
SAP

C_TSCM44_65 · Question #2

Your customer wants to see feasible receipt quantities in a "confirmed production" key figure in DP. What do you have to do to fulfill this request?

The correct answer is B. Implement SNP or PP/DS. The "release to demand planning" transaction with key figure. See the full explanation below for the reasoning.

Question

Your customer wants to see feasible receipt quantities in a "confirmed production" key figure in DP. What do you have to do to fulfill this request?

Options

  • AImplement PP/DS. Only finite scheduled PP/DS orders can be used with "collaborate into
  • BImplement SNP or PP/DS. The "release to demand planning" transaction with key figure
  • CImplement GATP. Confirmed quantities can then be updated periodically via the internal
  • DImplement SNP. Only SNP can interact with DP since the time series liveCache is required.

How the community answered

(62 responses)
  • A
    5% (3)
  • B
    74% (46)
  • C
    6% (4)
  • D
    15% (9)

Community Discussion

No community discussion yet for this question.

Full C_TSCM44_65 Practice