Question
How do you ensure that PP/DS planned orders retain the end date and quantity of previously created SNP orders?
Options
- AEnter the same value for the SNP production horizon and PP/DS horizon.
- BActivate "determine date and quantity based on SNP order" in Model and Version
- CUse transaction /SAPAPO/SNP2PPDS or interactive function "SNP order conversion".
- DMaintain the SNP production horizon to start at least 1 day before the PP/DS horizon ends.