Why do you need to create planned independent requirements (PIRs) based on DP forecast data? Note: There are 3 correct answers to this question.

The correct answer is B. For the GATP check against PIRs D. For planning in SNP or PP/DS E. For transferring to SAP ECC Demand Management for ECC MRP planning. See the full explanation below for the reasoning.

Question

Why do you need to create planned independent requirements (PIRs) based on DP forecast data? Note: There are 3 correct answers to this question.

Options

  • AFor the GATP check against ATP time series
  • BFor the GATP check against PIRs
  • CFor the CTP check
  • DFor planning in SNP or PP/DS
  • EFor transferring to SAP ECC Demand Management for ECC MRP planning

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    75% (21)
  • C
    18% (5)