C_TSCM44_65 · Question #42

The customer needs an SNP planning area for time-dependent safety stocks and scheduling agreements. As well as maintaining a time-dependent safety stock method in the product master, what else do…

The correct answer is B. Copy planning area 9ASNP03 with planning object structure 9ASNPSA into a. See the full explanation below for the reasoning.

Question

The customer needs an SNP planning area for time-dependent safety stocks and scheduling agreements. As well as maintaining a time-dependent safety stock method in the product master, what else do you have to do?

Options

  • ACopy planning area 9ASNP03 with planning object structure 9ASNPSA into a
  • BCopy planning area 9ASNP03 with planning object structure 9ASNPSA into a
  • CCopy planning area 9ASNP02 with planning object structure 9ASNPBAS into a
  • DCopy planning area 9ASNP02 with planning object structure 9ASNPBAS into a

How the community answered

(50 responses)
  • A
    8% (4)
  • B
    74% (37)
  • C
    14% (7)
  • D
    4% (2)