The customer wants to implement SNP aggregated planning for a product group with capacity leveling. What do you have to set up?

The correct answer is B. Hierarchies for products, locations, location products, and PPM/PDS. See the full explanation below for the reasoning.

Question

The customer wants to implement SNP aggregated planning for a product group with capacity leveling. What do you have to set up?

Options

  • AProduct hierarchies generated by ECC product groups that are transferred via CIF
  • BHierarchies for products, locations, location products, and PPM/PDS
  • CA planning area with time series for the aggregated orders
  • DHierarchies for products, locations, resources, and PPM/PDS

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    85% (29)
  • C
    6% (2)
  • D
    6% (2)