C_TSCM42_66 · Question #78
C_TSCM42_66 Question #78: Real Exam Question with Answer & Explanation
Sign in or unlock C_TSCM42_66 to reveal the answer and full explanation for question #78. The question stem and answer options stay visible for context.
Question
You want to produce a finished product only when it is requested by a customer order in make-to- order production. However, all assemblies need to be procured beforehand. How can you fulfill these requirements in SAP ECC? (Choose two)
Options
- AUse strategy 50 (planning without final assembly) for the finished product and no strategy for all
- BUse strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly
- CUse strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the
- DUse strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the
Unlock C_TSCM42_66 to see the answer
You've previewed enough free C_TSCM42_66 questions. Unlock C_TSCM42_66 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.