Which functions can be triggered before releasing a production order? (Choose three)

The correct answer is A. Selection of a routing B. Selection of a BOM E. Scheduling. See the full explanation below for the reasoning.

Question

Which functions can be triggered before releasing a production order? (Choose three)

Options

  • ASelection of a routing
  • BSelection of a BOM
  • CStock determination
  • DConfirmation
  • EScheduling

How the community answered

(59 responses)
  • A
    75% (44)
  • C
    8% (5)
  • D
    17% (10)

Community Discussion