What could be a consequence of confirming an operation?
The correct answer is B. The capacity requirements are updated. See the full explanation below for the reasoning.
Question
What could be a consequence of confirming an operation?
Options
- AThe planned costs are updated
- BThe capacity requirements are updated
- CThe production order is rescheduled
- DThe actual costs are settled
How the community answered
(34 responses)- A3% (1)
- B82% (28)
- C9% (3)
- D6% (2)