C_TSCM42_66 · Question #68
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for…
The correct answer is D. Alternative sequence. See the full explanation below for the reasoning.
Question
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40. Which sequence category do you use to create the second sequence in the system?
Options
- AFinish-start relationship
- BStandard sequence
- CParallel sequence
- DAlternative sequence
How the community answered
(37 responses)- A5% (2)
- B8% (3)
- C14% (5)
- D73% (27)