What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)

The correct answer is A. The order is no longer relevant for material requirements planning. B. Capacity requirements are set to null. D. Reservations are no longer relevant for material requirements planning. See the full explanation below for the reasoning.

Question

What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)

Options

  • AThe order is no longer relevant for material requirements planning.
  • BCapacity requirements are set to null.
  • CConfirmations are no longer possible.
  • DReservations are no longer relevant for material requirements planning.
  • EThe order and its operations receive the system status Locked (LKD).

How the community answered

(40 responses)
  • A
    83% (33)
  • C
    5% (2)
  • E
    13% (5)

Community Discussion