C_TSCM42_66 · Question #65
The final assembly of a finished product should only be triggered when a customer order arrives. Which planning strategy for the finished product do you use?
The correct answer is C. Planning without final assembly (strategy 50). See the full explanation below for the reasoning.
Question
The final assembly of a finished product should only be triggered when a customer order arrives. Which planning strategy for the finished product do you use?
Options
- APlanning with make-to-stock (strategy 10)
- BPlanning at the assembly level (strategy 70)
- CPlanning without final assembly (strategy 50)
- DPlanning with final assembly (strategy 40)
How the community answered
(21 responses)- A5% (1)
- B14% (3)
- C76% (16)
- D5% (1)