C_TSCM42_66 · Question #62

You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?

The correct answer is A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements. See the full explanation below for the reasoning.

Question

You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?

Options

  • ASales and operations planning -> Demand management -> Long-term planning -> Material requirements
  • BDemand management -> Sales and operations planning -> Capacity planning -> Long-term planning ->
  • CMaterial requirements planning -> Demand management -> Sales and operations planning -> Long-term
  • DLong-term planning -> Sales and operations planning -> Demand management -> Material requirements

How the community answered

(50 responses)
  • A
    76% (38)
  • B
    12% (6)
  • C
    4% (2)
  • D
    8% (4)