Which of the following master data can be used with process orders? (Choose three)

The correct answer is B. Master recipes C. Resources E. Production versions. See the full explanation below for the reasoning.

Question

Which of the following master data can be used with process orders? (Choose three)

Options

  • ASerial numbers
  • BMaster recipes
  • CResources
  • DProduction/resource tools
  • EProduction versions

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    82% (27)
  • D
    12% (4)

Community Discussion