SAP
C_TSCM42_66 · Question #61
Which of the following master data can be used with process orders? (Choose three)
The correct answer is B. Master recipes C. Resources E. Production versions. See the full explanation below for the reasoning.
Question
Which of the following master data can be used with process orders? (Choose three)
Options
- ASerial numbers
- BMaster recipes
- CResources
- DProduction/resource tools
- EProduction versions
How the community answered
(33 responses)- A6% (2)
- B82% (27)
- D12% (4)
Community Discussion
No community discussion yet for this question.