C_TSCM42_66 · Question #50

Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)

The correct answer is B. Automatic selection of the production version in material requirements planning (MRP) using the selection C. Automatic selection of the production version by applying quota arrangement records in material E. Manual assignment of planned production quantities in a planning table. See the full explanation below for the reasoning.

Question

Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system, and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)

Options

  • AAutomatic selection of the production line assigned to the MRP group used during material requirements
  • BAutomatic selection of the production version in material requirements planning (MRP) using the selection
  • CAutomatic selection of the production version by applying quota arrangement records in material
  • DA planning algorithm from capacity planning
  • EManual assignment of planned production quantities in a planning table

How the community answered

(32 responses)
  • A
    22% (7)
  • B
    72% (23)
  • D
    6% (2)