C_TSCM42_66 · Question #42
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the…
The correct answer is B. By the firming mechanism with the longer firming interval. See the full explanation below for the reasoning.
Question
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master. How is the resulting firming interval specified in this scenario?
Options
- ABy the planning time fence from the material master
- BBy the firming mechanism with the longer firming interval
- CBy the manual firming date
- DIt is predefined in Customizing.
How the community answered
(18 responses)- A6% (1)
- B78% (14)
- C6% (1)
- D11% (2)