C_TSCM42_66 · Question #41

What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)

The correct answer is A. ATP checks can be carried out automatically when releasing a production order. E. ATP checks can be adjusted to also consider future requirements and receipts. See the full explanation below for the reasoning.

Question

What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)

Options

  • AATP checks can be carried out automatically when releasing a production order.
  • BATP checks are automatically performed during Material Requirements Planning (MRP) runs.
  • CATP checks are used to evaluate the free capacity on a certain work center.
  • DATP checks are mandatory for lead-time scheduling.
  • EATP checks can be adjusted to also consider future requirements and receipts.

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    3% (1)
  • D
    10% (3)

Community Discussion

No community discussion yet for this question.