nerdexam
SAP

C_TSCM42_66 · Question #18

Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

The correct answer is C. Confirming the operation D. Setting the status technically complete (TECO) E. Reducing the order quantity. See the full explanation below for the reasoning.

Question

Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

Options

  • ARescheduling the operation
  • BPosting the goods receipt for the production order
  • CConfirming the operation
  • DSetting the status technically complete (TECO)
  • EReducing the order quantity

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    13% (4)
  • C
    80% (24)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_66 Practice