nerdexam
SAP

C_TSCM42_66 · Question #17

In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of…

The correct answer is C. There is no valid production version for this material. See the full explanation below for the reasoning.

Question

In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot). What could be the reason?

Exhibit

C_TSCM42_66 question #17 exhibit

Options

  • AThere are no planned orders or production orders present.
  • BThe repetitive manufacturing indicator has been set.
  • CThere is no valid production version for this material.
  • DThere are no requirements present.

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    74% (25)
  • D
    15% (5)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_66 Practice