nerdexam
SAP

C_TSCM42_65 · Question #21

Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two.)

The correct answer is B. ATP checks can be adjusted to also consider future requirements and receipts. D. ATP checks can be carried out automatically when releasing a production order. See the full explanation below for the reasoning.

Question

Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two.)

Options

  • AATP checks are automatically performed during MRP (Material Requirements Planning) runs.
  • BATP checks can be adjusted to also consider future requirements and receipts.
  • CATP checks are used to evaluate the free capacity on a certain work center.
  • DATP checks can be carried out automatically when releasing a production order.
  • EATP checks are mandatory for lead-time scheduling.

How the community answered

(42 responses)
  • A
    14% (6)
  • B
    74% (31)
  • C
    5% (2)
  • E
    7% (3)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_65 Practice