The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10…

The correct answer is B. Alternative sequence. See the full explanation below for the reasoning.

Question

The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?

Options

  • ASubstitute sequence
  • BAlternative sequence
  • CParallel sequence
  • DStandard sequence

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    75% (21)
  • C
    7% (2)
  • D
    14% (4)