SAP
C_TSCM42_65 · Question #16
C_TSCM42_65 Question #16: Real Exam Question with Answer & Explanation
Sign in or unlock C_TSCM42_65 to reveal the answer and full explanation for question #16. The question stem and answer options stay visible for context.
Question
The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?
Options
- ASubstitute sequence
- BAlternative sequence
- CParallel sequence
- DStandard sequence
Unlock C_TSCM42_65 to see the answer
You've previewed enough free C_TSCM42_65 questions. Unlock C_TSCM42_65 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.