Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
The correct answer is C. Set "Container full". See the full explanation below for the reasoning.
Question
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
Options
- ASet "Container in transport"
- BSet "Container empty"
- CSet "Container full"
- DSet "Container in process"
How the community answered
(49 responses)- A6% (3)
- B12% (6)
- C80% (39)
- D2% (1)