nerdexam
SAP

C_TSCM42_65 · Question #151

Which statements regarding SAP ECC long-term planning (LTP) are correct? (Choose two)

The correct answer is B. Reorder point planned materials can be included in LTP. D. A planning scenario must be released to use it in LTP. See the full explanation below for the reasoning.

Question

Which statements regarding SAP ECC long-term planning (LTP) are correct? (Choose two)

Options

  • AIn case of external procurement, LTP creates purchase requisitions.
  • BReorder point planned materials can be included in LTP.
  • CGenerally, LTP is operational planning of important components.
  • DA planning scenario must be released to use it in LTP.

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    73% (19)
  • C
    19% (5)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_65 Practice