Which master data is necessary for the creation of material reservations for production orders?

The correct answer is A. Material master records. See the full explanation below for the reasoning.

Question

Which master data is necessary for the creation of material reservations for production orders?

Options

  • AMaterial master records
  • BRoutings
  • CProduction versions
  • DProduction/resource tools

How the community answered

(30 responses)
  • A
    70% (21)
  • B
    13% (4)
  • C
    10% (3)
  • D
    7% (2)