C_TSCM42_65 · Question #136
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type…
The correct answer is A. If procurement type E (in-house production) is set, external procurement may still be possible depending D. If both procurement types are allowed with entry X (both procurement types), requirements planning. See the full explanation below for the reasoning.
Question
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system. Which of the following procurement type properties are valid? (Choose two)
Options
- AIf procurement type E (in-house production) is set, external procurement may still be possible depending
- BA material's procurement type can be freely selected between E (in-house production), F (external
- CProcurement types E (in-house production) and F (external procurement) have to be further refined with
- DIf both procurement types are allowed with entry X (both procurement types), requirements planning
How the community answered
(26 responses)- A81% (21)
- B4% (1)
- C15% (4)