Question
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
Options
- ALead time scheduling cannot take place.
- BRequirements planning creates an appropriate exception message in basic dates scheduling.
- CSubsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
- DDependent requirements request the components from the bill of materials at wrong times when using