C_TSCM42_65 · Question #132
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
The correct answer is D. Dependent requirements request the components from the bill of materials at wrong times when using. See the full explanation below for the reasoning.
Question
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
Options
- ALead time scheduling cannot take place.
- BRequirements planning creates an appropriate exception message in basic dates scheduling.
- CSubsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
- DDependent requirements request the components from the bill of materials at wrong times when using
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C12% (3)
- D80% (20)