Question

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence. What do you have to consider in this scenario?

Options

  • APlanned orders that are created by requirements planning are shifted to the end of the planning time
  • BRequirements planning considers only changes that are relevant for scheduling within the planning time
  • CThe MRP controller cannot create planned orders within the planning time fence.
  • DPlanned orders are created within the planning time fence and automatically firmed by requirements

Unlock C_TSCM42_65 to see the answer

You've previewed enough free C_TSCM42_65 questions. Unlock C_TSCM42_65 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.