Which properties does ECC Master Production Scheduling (MPS) have? (Choose three)

The correct answer is B. Non-MPS items can be taken into consideration by an MPS run. D. MPS items can be defined on MRP Area level. E. MPS items can be defined on plant level. See the full explanation below for the reasoning.

Question

Which properties does ECC Master Production Scheduling (MPS) have? (Choose three)

Options

  • AMPS items can be taken into consideration by a standard MRP run.
  • BNon-MPS items can be taken into consideration by an MPS run.
  • CThe planning of MPS and Non-MPS items is always carried out in one planning run.
  • DMPS items can be defined on MRP Area level.
  • EMPS items can be defined on plant level.

How the community answered

(20 responses)
  • A
    20% (4)
  • B
    70% (14)
  • C
    10% (2)

Community Discussion