You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you should be able to use a second sequence on other work centers for…

The correct answer is C. Alternative sequence. See the full explanation below for the reasoning.

Question

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you should be able to use a second sequence on other work centers for operations 30 and 40. What sequence category do you use to create the second sequence in the system?

Options

  • ASubstitute sequence
  • BStandard sequence
  • CAlternative sequence
  • DParallel sequence

How the community answered

(31 responses)
  • A
    16% (5)
  • B
    3% (1)
  • C
    74% (23)
  • D
    6% (2)