Which of the following scheduling types can only be used within capacity planning?
The correct answer is D. Midpoint. See the full explanation below for the reasoning.
Question
Which of the following scheduling types can only be used within capacity planning?
Options
- AForwards
- BOnly capacity requirements
- CBackwards
- DMidpoint
How the community answered
(53 responses)- A4% (2)
- B15% (8)
- C8% (4)
- D74% (39)