SAP
C_TSCM42_65 · Question #115
Which of the following properties applies to multi-site planning in SAP ECC?
The correct answer is B. Both withdrawal from alternative plant and stock transfer from another plant are defined via special. See the full explanation below for the reasoning.
Question
Which of the following properties applies to multi-site planning in SAP ECC?
Options
- AMulti-site planning can be activated using the corresponding planning strategy.
- BBoth withdrawal from alternative plant and stock transfer from another plant are defined via special
- CThe use of "scope of planning" (cross-plant total planning) is mandatory for multi-site planning.
- DWhen using one-step stock transfer posting, transfer stock is created in the receiving plant.
How the community answered
(64 responses)- A11% (7)
- B81% (52)
- C3% (2)
- D5% (3)
Community Discussion
No community discussion yet for this question.